Medupi vs Wind Farm

Graph shows: Capacity factor/availability of plant: Wind Farm vs Medupi

 

 

Year

Capacity factor/availability of plant (Medupi)

Capacity factor/availability of plant (80MW Wind Farm) assuming construction commenced with Medupi in May 2007

Construction starts

0

 

 

 

1

0%

0%

Wind farm commissioned after about 18-24 months

2

0%

0%

 

3

0%

25%

 

4

0%

35%

 

5

0%

40%

 

6

0%

40%

 

7

0%

40%

 

8

0%

40%

Medupi unit 1 synchronised

9

14%

40%

 

10

14%

40%

 

11

14%

40%

Medupi unit 2 synchronised

12

28%

40%

Medupi unit 3 synchronised

13

42%

40%

Medupi units 4 & 5 synchronised

14

70%

40%

Medupi unit 6 synchronised

15

84%

40%

 

16

84%

40%

 

17

84%

40%

 

18

84%

40%

 

19

84%

40%

 

20

84%

40%

 

21

84%

40%

Wind farm reaches end of life – rehabilitated or can be repowered

22

84%

0%

 

23

84%

0%/40%

 

24

84%

0%/40%

 

25

84%

0%/40%

 

26

84%

0%/40%

 

27

84%

0%/40%

 

28

84%

0%/40%

 

29

84%

0%/40%

 

30

84%

0%/40%